Multiple Choice
This is an explanation of the event or events that signal to the person monitoring that this risk is about to happen or has happened; it involves looking at the root cause of the risk.
A) Mitigation
B) Consequence
C) Probability
D) Trigger event
Correct Answer:

Verified
Correct Answer:
Verified