Multiple Choice
With this risk strategy, an organization can decide to accept the consequences if a risk occurs without trying to control it. In this situation, no mitigation strategy is deemed necessary, although you may set aside some contingency reserves for cost and schedule.
A) Risk avoidance
B) Risk acceptance
C) Risk transference
D) Risk mitigation