Multiple Choice
________ entails eliminating a specific threat or risk, usually by eliminating its causes, making a change in the design, making a change in requirements, or changing technology to remove the risk entirely. It's important to recognize that avoiding the risk may also avoid associated benefits.
A) Risk avoidance
B) Risk acceptance
C) Risk transference
D) Risk mitigation