Multiple Choice
These are the costs associated with system defects after the system is fully deployed (for example, scrap, rework, returns, market share, lawsuits) .
A) External failure costs
B) Internal failure costs
C) Cost of nonconformance
D) Cost of quality
Correct Answer:

Verified
Correct Answer:
Verified