The First Step in the Process Used to Build the Communications

Question 18

Multiple Choice

The first step in the process used to build the communications management plan is:


A) Review the stakeholder analysis and complete the stakeholder communications matrix.
B) Define content for status reports and timing.
C) Establish who is responsible for collecting data.
D) Establish key project team contacts.

Correct Answer: