    Which of the Following Is NOT an Analytical Technique Used
Solved

Which of the Following Is NOT an Analytical Technique Used

Question 5

Question 5

Multiple Choice

Which of the following is NOT an analytical technique used in determining project schedule?


A) PERT
B) Critical path method
C) Resource loading
D) Resource leveling

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q1: One drawback of the activity on arrow

Q2: List at least two advantages and two

Q3: The processes of PMBOK's Time Management knowledge

Q4: The last step in the process for

Q6: What is CPM and how is it

Q7: If a task has free slack it

Q8: Resource _ defines the amount of time

Q9: The precedence diagram method illustrates two types

Q10: Three-point estimating adds the element of _

Q11: Describe the insights regarding estimating offered by

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines