Multiple Choice
It is important for the project manager to understand the reasons why a project was selected so that the ________ for the project are clearly defined and understood.
A) resources
B) critical success factors
C) customers
D) executive sponsors
Correct Answer:

Verified
Correct Answer:
Verified