Multiple Choice
Which of the following is NOT a benefit of IT project portfolio management?
A) Capability to identify redundancies
B) Capability to allocate resources across all projects appropriately
C) Capability to monitor project progress
D) Capability to control project managers
Correct Answer:

Verified
Correct Answer:
Verified