Multiple Choice
Which of the following is NOT a strength of evolutionary prototyping life cycle?
A) Customers can see steady progress
B) Feedback from user reviews is timely
C) Allows for accurate cost estimating at the beginning
D) Helps gain customer commitment to a set of requirements