    All Projects Are Constrained by Their Scope, Time, and Cost
Solved

All Projects Are Constrained by Their Scope, Time, and Cost

Question 75

Question 75

Multiple Choice

All projects are constrained by their scope, time, and cost referred to as the ________ constraint.


A) project manager's
B) multiple
C) project
D) triple

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q69: Project management is only about concepts, tools,

Q70: Which of the following is NOT one

Q71: When it comes to project management, experience

Q72: Critical success factor(s) in running a successful

Q73: A project is a(n) _ sequence of

Q74: Opportunity cost refers to the resources being

Q76: The acronym PMP stands for:<br>A) Product Management

Q77: The matrix organization comes in which general

Q78: The determination of a weak to strong

Q79: In the 1990s, interest in project management

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines