Multiple Choice
PERT/CPM is called a(n) ____ technique, because it analyzes a large, complex project as a series of individual tasks.
A) top-down
B) bottom-up
C) indexed
D) cataloging
Correct Answer:

Verified
Correct Answer:
Verified