Multiple Choice
Microsoft's risk management model includes all of the following EXCEPT ____.
A) category, which specifies the risk type
B) probability, which indicates the degree of adverse effect should the risk occur, on a scale of 1 to 10
C) mitigation plan, which identifies plans to control or limit the risk
D) trigger, which identifies a condition that would initiate the contingency plan
Correct Answer:

Verified
Correct Answer:
Verified
Q2: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB5608/.jpg" alt=" -In the project
Q6: If any task along the critical path
Q10: A project manager's planning _.<br>A)involves guiding, supervising,
Q34: System developers can initiate a formal project
Q53: When two or more concurrent tasks depend
Q65: <img src="https://d2lvgg3v3hfg70.cloudfront.net/TB5608/.jpg" alt=" -To simplify a
Q73: If team members lack experience with certain
Q100: Microsoft offers a free _ trial version
Q101: When an information system does not meet
Q104: _ is open-source software that is supported