If the Project Team and Organizational Officials Reassess the Project

Question 117

Multiple Choice

If the project team and organizational officials reassess the project after each subsequent SDLC phase to determine if the business conditions have changed or if a more detailed understanding of a system's costs,benefits,and risks suggest that the project is not as worthy as previously thought,they are:


A) adhering to the incremental commitment principle
B) overly cautious
C) using a CASE methodology
D) adhering to a bottom-up commitment principle