Changes to the Baseline Project Plan Might Be Motivated By

Question 115

Multiple Choice

Changes to the Baseline Project Plan might be motivated by:


A) a slipped completion date of an activity
B) a bungled activity that must be redone
C) the identification of a new activity that becomes evident later in the project
D) all of the above

Correct Answer:

verifed

Verified