Which of the following is NOT a feature of PERT?


A) Uses optimistic estimate
B) Uses pessimistic estimate
C) Uses realistic estimate
D) Calculates budget for a project

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q45: The last deliverable,or end product,produced by Chris

Q46: The project charter often includes a signature

Q47: Which of the following is NOT a

Q48: What does a project manager do during

Q49: The Project Workbook is an offline or

Q51: _ is NOT a skill pertaining to

Q52: What is a project manager? What types

Q53: A _ is a planned undertaking of

Q54: COCOMO stands for _.<br>A)Constructive Coordination Model<br>B)Constructive Cost

Q55: What are some of the activities one

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines