Multiple Choice
To construct the Gantt chart,a ________ is drawn for each activity that reflects its sequence and duration.
A) Horizontal line
B) Horizontal bar
C) Vertical line
D) Vertical bar
Correct Answer:

Verified
Correct Answer:
Verified