If Your Project Will Take 15 Hours to Complete, Your

Question 13

Multiple Choice

If your project will take 15 hours to complete, your hourly billing rate is set at $75, and you will divide the work over three days, how much should you estimate for the project cost?


A) $375
B) $1,125
C) $225
D) $3,375