Essay
Exhibit 11-2
Suppose we want to choose capacity for a plant that will produce a new drug. In particular, we want to choose the capacity that maximizes discounted expected profit over the next 10 years. Assume all cash flows occur at the end of the year. We have the following information:
∙Demand for the drug is expected to be normally distributed ˜ Normal (50,000, 12,000). Demand each year is an independent event.
∙A unit of capacity costs $16 to build in year 1.
∙The number of units produced will equal the demand, up to capacity limits.
∙The revenue per unit is $3.70 and the cost per unit is $0.20 (variable cost).
∙The maintenance cost per unit of capacity is $0.40 (fixed cost).
∙The discount rate is 10%.
-[Part 1] Refer to Exhibit 11-2.Perform a simulation assuming the plant will be designed to meet the expected demand.What is the net present value (NPV)in that case
Correct Answer:

Verified
The output below sho...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q4: Exhibit 11-1<br>A company is considering investing $1.2M
Q5: The RISKSIMTABLE function is used to summarize
Q6: Which of the following is typically not
Q7: In bidding models,the simulation output variable is
Q8: A common distribution for modeling product lifetimes
Q11: For an NPV simulation,the value at risk
Q12: Value at risk (VAR)is an indicator of:<br>A) how
Q13: Which of the following is the most
Q14: Exhibit 11-2<br>Suppose we want to choose capacity
Q52: In financial simulation models,we are typically more