Multiple Choice
A bank of ten machines requires regular periodic service.Machine running time and service time are both exponential.Machines run for an average of 44 minutes between service requirements,and service time averages 6 minutes per machine. What is the average machine downtime with two operators?
A) 1.71 minutes
B) 3.46 minutes
C) 6.25 minutes
D) 7.71 minutes
E) 9.46 minutes