A bank is designing a new branch office and needs to determine how much driveway space to allow for cars waiting for drive up teller service.The drive up service will have three tellers and a single waiting line.At another branch of the bank in a similar setting,the average service time for drive up tellers is 4 minutes per customer and average arrival rate is 36 customers per hour.It is expected that the new bank will have similar characteristics. For how many tellers should the system be designed if the managers want the average time a customer spends in the system to be no more than 5 minutes?


A) at least 3
B) at least 4
C) at least 5
D) at least 6
E) It is impossible to say without more information.