Multiple Choice
A project manager for Durable Construction Co.is about to build a house involving the following six activities: What is the estimated expected (mean) duration for project completion?
A) 160 days
B) 170 days
C) 200 days
D) 210 days
E) 300 days
Correct Answer:

Verified
Correct Answer:
Verified