Essay
Activity E has an optimistic duration of 9 days,a most likely duration of 12 days,and a pessimistic duration of 15 days.Estimate its expected duration and standard deviation.
Correct Answer:

Verified
te = (t0 + 4tm + tp)/6 =...View Answer