Activity E Has an Optimistic Duration of 9 Days,a Most

Question 121

Essay

Activity E has an optimistic duration of 9 days,a most likely duration of 12 days,and a pessimistic duration of 15 days.Estimate its expected duration and standard deviation.

Correct Answer:

verifed

Verified

te = (t0 + 4tm + tp)/6 =...