Multiple Choice
Which of the following is the last step in the production planning hierarchy before actual output is produced?
A) Material requirements planning.
B) Enterprise resource planning.
C) Capacity planning.
D) Aggregate planning.
E) Scheduling.
Correct Answer:

Verified
Correct Answer:
Verified