Multiple Choice
The purpose of a Gantt chart is to:
A) visually express the capacity of resources.
B) quantitatively analyze the optimum sequencing of resources.
C) visually represent the loading and scheduling of jobs for control purposes.
D) quantitatively analyze the capacity of production resources.
E) visually express the material allocation at work centres.
Correct Answer: