Multiple Choice
Average job flow time for a schedule sequence at a work station is:
A) total processing time divided by the number of jobs.
B) total flow time divided by the number of jobs.
C) total flow time divided by total processing time.
D) total processing time plus total late time divided by number of jobs.
E) total flow time plus total late time divided by number of jobs.
Correct Answer:

Verified
Correct Answer:
Verified