The scheduling sequencing rule which always results in the lowest average flow (flow) time is the:
A) critical ratio (CR) .
B) earliest due date (EDD) .
C) first come,first serve (FCFS) .
D) minimum slack time (MST) .
E) shortest processing time (SPT) .