Multiple Choice
Material requirements planning (MRP) is an example of a(n) :
A) push system.
B) pull system.
C) backward communications approach.
D) inventory accumulation approach.
E) forecasting process for finished goods
Correct Answer:

Verified
Correct Answer:
Verified