    The Hierarchical Diagram That Depicts the Subassemblies and Components That
Solved

The Hierarchical Diagram That Depicts the Subassemblies and Components That

Question 77

Question 77

Multiple Choice

The hierarchical diagram that depicts the subassemblies and components that are needed to produce and/or assemble a product is called a(n) :


A) assembly time chart.
B) product structure tree.
C) MRP II.
D) pegging.
E) assembly diagram

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q68: Safety time is sometimes used in MRP

Q69: Independent demand tends to be _,while dependent

Q70: Which of these products and services would

Q71: A bill of material contains a listing

Q72: ERP packages are intended to fit established

Q73: Great Product,Ltd.has just received an order for

Q74: Dependent demand tends to be intermittent,whereas independent

Q75: Independent demand tends to be more sporadic

Q76: Under fixed-interval lot sizing,order sizes for component

Q78: Given an order cost of $100,a,per period

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines