Multiple Choice
Ignoring the possibility of safety stock requirements,which one of the following most closely describes the calculation of net requirements for an item in MRP?
A) Gross requirements - projected on-hand - scheduled receipts
B) Gross requirements - scheduled receipts
C) Gross requirements - order releases + amount on-hand
D) Gross requirements - planned order releases
E) Gross requirements - projected on-hand + planned order releases
Correct Answer:

Verified
Correct Answer:
Verified