Multiple Choice
Which action would not be undertaken if capacity requirements planning (CRP) indicate one or more work stations are projected to be under loaded or over loaded?
A) Shifting some orders to adjacent periods.
B) Transferring employees from other areas.
C) Scheduling overtime.
D) Revise the MPS and MRP.
E) Re-run the load report using different values.
Correct Answer:

Verified
Correct Answer:
Verified