Great Product,Ltd

Question 16

Multiple Choice

Great Product,Ltd.has just received an order for 100 Whozats,which must be ready for delivery at the start of week six.An MRP planner has prepared the following table showing product structure,lead times (orders are lot-for-lot) ,and quantities on hand: Great Product,Ltd.has just received an order for 100 Whozats,which must be ready for delivery at the start of week six.An MRP planner has prepared the following table showing product structure,lead times (orders are lot-for-lot) ,and quantities on hand:   How many Wherezats should be ordered? A) 400 B) 450 C) 500 D) 550 E) 600 How many Wherezats should be ordered?


A) 400
B) 450
C) 500
D) 550
E) 600

Correct Answer:

verifed

Verified