Multiple Choice
For a process to be capable,it must have a capability ratio of at least 1.00.A ratio of 1.00 implies that what percent of the output of a process can be expected to be within the design specification limits?
A) 66.67%
B) 73.33%
C) 95.54%
D) 99.74%
E) 100%
Correct Answer:

Verified
Correct Answer:
Verified
Q8: Given the following process control data for
Q9: Design specifications are equivalent to control limits.
Q10: The output of a process may not
Q11: The range chart (R-chart)is most likely to
Q12: Variation in a sample statistic collected from
Q14: The term "2 sigma limits" in the
Q15: Quality control efforts that occur during production
Q17: Control limits and process variability are directly
Q18: The frequency and quantity of inspection depends
Q83: "Assignable variation" is variation due to a