Multiple Choice
A Methods and Measurements Analyst needs to develop a time standard for a certain task.In a preliminary study,he observed one of his employees perform this task five times,with the following results: What is the observed time (OT) for this task?
A) 80 seconds
B) 84 seconds
C) 160 seconds
D) 240 seconds
E) 400 seconds
Correct Answer:

Verified
Correct Answer:
Verified
Q122: A work sampling study of dockworkers must
Q123: The behavioural approach to job design which
Q124: Piece rate pays are a common type
Q125: The criteria for the Healthy Workplace Award
Q126: Slow motion studies are useful for training
Q128: 11eab92b_c497_b413_99e6_bd88084db4cb What is the observed time for
Q129: The owner of Kat Motel wants to
Q130: Which of the following is not an
Q131: A job had an observed time of
Q132: The work measurement technique that counts the