Multiple Choice
A Methods and Measurements Analyst needs to develop a time standard for a certain task.In a preliminary study,he observed one of his employees perform this task five times,with the following results: What is the standard time (ST) for this task if the employee worked at a twenty-five percent faster pace than the average and an allowance of twenty percent of job time is used?
A) 80 seconds
B) 96 seconds
C) 100 seconds
D) 120 seconds
E) 125 seconds
Correct Answer:

Verified
Correct Answer:
Verified
Q12: Predetermined time standards involve the use of
Q13: Methods-time measurement (MTM)requires analysts to collect multiple
Q14: The owner of Touchdown Sports Bar wants
Q15: Research has shown that unmet human needs
Q16: 11eab92b_c497_db28_99e6_fb7d78a5ddfb How many observations would be needed
Q18: Output-based pay compensates employees according to the
Q19: The name Frederick Winslow Taylor is associated
Q20: A job has a normal time of
Q22: Flow process charts can be useful for
Q36: In work sampling, observations should be taken:<br>A)at