Solved

A Company Is Designing a Product Layout for a New

Question 168

Multiple Choice

A company is designing a product layout for a new product.It plans to use this production line eight hours a day in order to meet projected demand of 480 units per day.The tasks necessary to produce this product: A company is designing a product layout for a new product.It plans to use this production line eight hours a day in order to meet projected demand of 480 units per day.The tasks necessary to produce this product:   Without regard to demand,what is the minimum possible cycle time (in seconds) for this situation? A) 162 B) 72 C) 54 D) 12 E) 60 Without regard to demand,what is the minimum possible cycle time (in seconds) for this situation?


A) 162
B) 72
C) 54
D) 12
E) 60

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge