Multiple Choice

A company is designing a product layout for a new product.It plans to use this production line eight hours a day in order to meet projected demand of 480 units per day.The tasks necessary to produce this product: A company is designing a product layout for a new product.It plans to use this production line eight hours a day in order to meet projected demand of 480 units per day.The tasks necessary to produce this product:   If the company desires that output rate equal demand,what would the percentage idle time of this line be with the minimum number of workstations? A) 0% B) 7.5% C) 1% D) 12.5% E) 10% If the company desires that output rate equal demand,what would the percentage idle time of this line be with the minimum number of workstations?


A) 0%
B) 7.5%
C) 1%
D) 12.5%
E) 10%

Correct Answer:

verifed

Verified

Unlock this answer now