A company is designing a product layout for a new product.It plans to use this production line eight hours a day in order to meet projected demand of 480 units per day.The tasks necessary to produce this product: If the company desires that output rate equal demand,what is the last task performed in the first workstation in the balance which uses the minimum number of workstations?
A) u
B) v
C) w
D) x
E) y
Correct Answer: