Multiple Choice
The first product took 10 hours to build and the learning curve is estimated to be 90%. How long with it take to make the fourth unit?
A) 10 hours
B) 9 hours
C) 8.1 hours
D) 7.5 hours
E) none of the above
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q25: What cautions are in order when using
Q29: If the learning curve for a process
Q51: The second unit of production took 9
Q53: If it took 1000 hours to produce
Q67: When comparing a 70% learning curve versus
Q79: Your firm has a contract to make
Q81: Suppose that there are two products with
Q82: Which of the following is <b>not</b> a
Q88: You are about to undertake manufacture of
Q89: What is the basic premise underlying the