Multiple Choice
The first unit of a product took 832 hours to build, and the learning curve is 90%. How long will it take to make the 25th unit? (Use at least three decimals in the exponent if you use the logarithmic approach.)
A) time ≤ 500 hours
B) 500 < time ≤ 525
C) 525 < time ≤ 530
D) 530 < time ≤ 550
E) time > 550