Essay
You have been asked to balance a flow shop assembly operation to achieve an output rate of 80 units per eight-hour day. Task times and precedence relationships are shown in the table below.
a. Draw the precedence diagram.
b. Determine the desired cycle time.
c. Determine the theoretical minimum number of stations needed.
d. Balance this line using most following tasks.
e. What is the efficiency of the line obtained in part d?
Correct Answer:

Verified
The precedence diagram appears...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q37: A hospital's layout most closely resembles which
Q54: What is the primary reason why retailers
Q61: Identify the four requirements for cellular production.
Q62: One of the major advantages of process-oriented
Q72: Cross-docking is<br>A) seldomly placing an item in
Q74: Briefly explain what "slotting" is. Why is
Q76: _ are fees manufacturers pay to get
Q97: For which of the following operations would
Q122: What are the two basic types of
Q267: The minimum number of workstations depends upon