Essay
An assembly line with 11 tasks is to be balanced.The longest task is 2.4 minutes,the shortest task is 0.4 minutes,and the sum of the task times is 18 minutes.The line will operate for 600 minutes per day.
(a)Determine the minimum and maximum cycle times.
(b)What range of output is theoretically possible for the line?
(c)What is the minimum number of stations needed if the maximum output rate is to be sought?
(d)What cycle time will provide an output rate of 200 units per day?
Correct Answer:

Verified
(a)Minimum cycle time is 2.4 minutes.Max...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q10: If the schedule calls for the production
Q11: One guideline for a retail layout is
Q12: An electronics manufacturer makes remote control devices
Q17: There are three work centers (A,B,and C)behind
Q18: An assembly line has been designed to
Q19: In assembly-line balancing,the theoretical minimum number of
Q172: The layout approach that addresses trade-offs between
Q221: A(n) _ addresses flow, allocates space, and
Q224: A process-oriented layout is the traditional way
Q228: If a layout problem is solved by