Essay
Given the following chart of jobs assigned with Johnson's rule suppose that all the jobs (A, B, C, etc) could be evenly divided into two tasks (such as A1 and A2, B1 and B2, etc). Suppose job B is divided into jobs B1 and B2, each with a body work time of 4.5 hours and a paint time of 2 hours. How much is makespan reduced by this splitting of B?
Correct Answer:

Verified
B1 could start on paint at time=34.5 (1/...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q4: Finite capacity scheduling allows virtually instantaneous changes
Q26: Which of the following is an aid
Q26: In manufacturing scheduling, physical inventories of goods
Q42: Explain, in your own words, what is
Q64: Which of the following statements regarding scheduling
Q69: Lockport Marine Services, Inc. wishes to assign
Q82: Because of the significance of labor in
Q89: Average completion time for a schedule sequence
Q109: The work-center master file contains data such
Q137: _ are used to schedule resources and