    Given the Following Bill of Material If the Demand
Solved

Given the Following Bill of Material If the Demand

Question 85

Question 85

Multiple Choice

Given the following bill of material Given the following bill of material   If the demand for product A is 30 units, and there are 10 units of B on hand and none of C, how many units of part D will be needed? A)  3 B)  40 C)  70 D)  90 E)  110 If the demand for product A is 30 units, and there are 10 units of B on hand and none of C, how many units of part D will be needed?


A) 3
B) 40
C) 70
D) 90
E) 110

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q8: What is MRP? Identify four benefits from

Q14: Jacquie Welkener,operations manager for ABC Technologies,must schedule

Q16: Capacity planning in closed-loop MRP:<br>A)utilizes feedback about

Q28: Firms making many different final products use

Q57: Which of the following regarding enterprise resource

Q82: The following table is an example of

Q97: MRP II is accurately described as<br>A) MRP

Q104: What is the "supermarket" as it is

Q116: What does enterprise resource planning (ERP) allow

Q135: In job shop (make-to-order) operations, the master

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines