Multiple Choice
It is week 1 and there are currently 20 As in stock. The MPS calls for 300 As at the start of week 5. If there are scheduled receipts planned for week 3 and week 4 of 120 As each and A has a lead time of 1 week when and how large of an order should be placed to meet the requirement of 300 As?
A) Week 1, 300 A s
B) Week 1, 40 A s
C) Week 5, 40 A s
D) Week 4, 40 A s
E) Week 4, 300 A s
Correct Answer:

Verified
Correct Answer:
Verified