Multiple Choice
For the lot-sizing technique known as lot-for-lot to be appropriate:
A) future demand should be known for several weeks.
B) setup cost should be relatively small.
C) annual volume should be rather low.
D) item unit cost should be relatively small.
E) the independent demand rate should be very stable.
Correct Answer:

Verified
Correct Answer:
Verified