Which of the following statements regarding MRP in services is true?
A) MRP is for manufacturing only, and is not applicable to services.
B) MRP can be used in services, but only those that offer very limited customization.
C) MRP does not work in services because there is no dependent demand.
D) Services such as restaurant meals illustrate dependent demand, and require product structure trees, bills-of-material, and scheduling.
E) None of the above is true.
Correct Answer: