Multiple Choice
A worker completed a job 10 times during a period in which a normal, trained employee completed the task 8 times. What is the worker's performance rating?
A) 125%
B) 150%
C) 100%
D) 112.5%
E) cannot be determined with given information
Correct Answer:

Verified
Correct Answer:
Verified