Essay
A Methods and Measurements Analyst needs to develop a time standard for a certain task. The task involves use of ruler, square, and portable electric saw to mark and cut the "notch" in a rafter (a standard carpentry task of home construction). In a preliminary study, he observed one of his workers perform this task five times. The observations were made in an air-conditioned, well-lighted training facility, at ground level, with all tools and equipment clean and readily available.
a. What is the actual average time for this task?
b. What is the normal time for this task if the employee worked at a 20% faster pace than is typical for adequately trained workers?
c. What is standard time for this task if allowances are 8% constant and 6% variable?
d. If the analyst then thought more carefully about his experiment, and decided that the variable allowances needed to be increased to match the real (outside, unair-conditioned) work environment, and that the proper variable allowance was not 6% but 12%, what is the revised standard time?
Correct Answer:

Verified
a. Actual average time is 79 s...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q2: _ involves timing a sample of a
Q8: The tally sheet data from a work
Q12: Describe some impacts of noise in the
Q65: It is said that job expansion has
Q71: _ is a means of determining staffing
Q88: How is the statistical tool of adequate
Q112: The accuracy of a labor standard is
Q153: A time-study procedure involves timing a sample
Q165: Technology, location, and layout decisions are all
Q189: Equitable pay alone cannot achieve a reasonable