A Project Manager Bases His Time and Labor Estimates on a Learning

Question 15

True/False

A project manager bases his time and labor estimates on a learning curve of 86%.The actual learning curve turns out to be 89%.The manager,because of the decreased learning,will complete his project in more time and with more labor use than his estimate suggested.