Essay
Cyclone Appliances has developed a new European-style convection oven that will be made on an assembly line.The schedule requires 80 ovens in an 8-hour day.The assembly includes seven tasks.The table below indicates the performance time and the sequence requirements for each task.
(a)What is the cycle time for this assembly operation?
(b)What is the theoretical minimum number of workstations?
(c)Draw the precedence diagram.
Correct Answer:

Verified
(a)The cycle time is 480 minutes per day...View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Correct Answer:
Verified
View Answer
Unlock this answer now
Get Access to more Verified Answers free of charge
Q10: If the schedule calls for the production
Q23: Balancing low-cost storage with low-cost material handling
Q34: The central problem in product-oriented layout planning
Q46: A production line is to be designed
Q66: To develop a good facility layout, what
Q124: Which of the following is NOT a
Q131: The fixed-position layout would be MOST appropriate
Q153: _ is the use of computer software
Q216: Why do work cells increase the utilization
Q221: A(n) _ addresses flow, allocates space, and